Active Projects Report - August 15, 2025

Los Rios CCD | Planning and Construction

ARC 2024 PE HVAC Upgrade
PM: Mirmiran Architect: Moniz Architecture Contractor:
Scope: Provide upgraded HVAC for mens locker room.
Weekly Update: Bid in progress. The project will have 4 components as follow: 1) FM Electrical has installed new 400 Amp panel. (Done) 2) FM has ordered the equipment.(Pending last unit to arrive) 3) ATI will be abating the roof assembly and ceiling. 4) Bid Documents will be issued for installation of the equipment.
Tenative Schedule Start Months Finish % Complete
Prelim Plans Dec 2024 1 Jan 2025 100%
Approvals Jan 2025 1 Feb 2025 100%
Working Drawings Feb 2025 4 Jun 2025 100%
Approvals Jun 2025 1 Jul 2025 100%
Bid and Award Jul 2025 1 Aug 2025 15%
Construction Aug 2025 1 Sep 2025 0%
Campus Move-in Sep 2025 0 Sep 2025 0%
ARC 2025 BSO Office Remodel
PM: Blake Architect: Moniz Architecture Contractor:
Scope: Campus requested and funded remodel of area within the Business Services Office including ADA upgrades.
Weekly Update: 2025.08.11- 1) Contacted Pro Builders & BP Interiors on providing a Quote under a Small Business Delivery Method, conducted Bid/Quote Walk on Wednesday 8/6/25 at 12pm., RFI's are due by Monday 8/11/25 at 2pm, RFI Replies are due by Wednesday 8/13/25 2pm, quotes due on Friday 8/15/25 at 2pm.
Tenative Schedule Start Months Finish % Complete
Prelim Plans Mar 2025 1 Apr 2025
Approvals Apr 2025 1 May 2025
Working Drawings May 2025 1 Jun 2025
Approvals Jun 2025 1 Jul 2025
Bid and Award Jul 2025 1 Aug 2025
Construction Aug 2025 3 Nov 2025
Campus Move-in Nov 2025 1 Dec 2025
ARC 2025 Child Development Center Shade Structure
PM: Uhlmeyer Architect: Architechnica Contractor:
Scope: Project to replace old failing shade structures at CDC.
Weekly Update: DSA Submittal 8/28 - OTC 9/5 &%% plans received for review/approval 7/30/2025 Concept Drawing Received 5/27/2025 & shared with Campus 6/4 Design "Kick Off" meeting held on 5/13/2025
Tenative Schedule Start Months Finish % Complete
Prelim Plans May 2025 2 Jul 2025 100%
Approvals Jul 2025 1 Aug 2025 100%
Working Drawings Aug 2025 4 Dec 2025 75%
Approvals Dec 2025 2 Feb 2026
Bid and Award Feb 2026 3 May 2026
Construction May 2026 4 Sep 2026
Campus Move-in Sep 2026 1 Oct 2026
ARC 2025 Natomas Key and Card Access Upgrade
PM: Blake Architect: Contractor:
Scope:
Weekly Update: 2025.08.11- 1) Due to a lot of the work was already completed inhouse prior, FM Electrical/Structural teams will be performing the labor and providing an estimate for materials. 2) Provided FM teams with scope of work documents for takeoffs. 3) Electrical Teams materials and labor work is complete less the final connections to the Key Box. 4) Received Key Box Quote from Structural, put in for a P.O. with Purchasing on 5/16/25. 5) Waiting for Structural to provide Door Hardware materials quote.
Tenative Schedule Start Months Finish % Complete
Prelim Plans Mar 2025 3 Jun 2025
Approvals Jun 2025 1 Jul 2025
Working Drawings Jul 2025 1 Aug 2025
Approvals Aug 2025 1 Sep 2025
Bid and Award Sep 2025 1 Oct 2025
Construction Oct 2025 1 Nov 2025
Campus Move-in Nov 2025 1 Dec 2025
ARC Astroturf Synthetic Softball Field
PM: Uhlmeyer Architect: LPA Contractor: PROGRASS WEST INC
Scope: In an effort to address sustainability goals and improve facilities for Los Rios students this project will replace the exist ing natural grass softball fields at American River College, Sacramento City College and Folsom Lake College with a new synthetic fields. The planned improvements include Removal of the existing natural grass field, New synthetic turf field with associated subdrainage, ADA path of travel improvements as required for the field and Minor ADA improvements to the existing restroom facilities.
Weekly Update: Field complete ---- ADA POT expected completion 1/17/2025 --- ADA Restroom modifications expected completion 1/14
Tenative Schedule Start Months Finish % Complete
Prelim Plans May 2022 4 Sep 2022 100
Approvals Sep 2022 1 Oct 2022 100
Working Drawings Oct 2022 2 Dec 2022 100
Approvals Dec 2022 2 Feb 2023 100
Bid and Award Feb 2023 3 May 2023 100
Construction May 2023 5 Oct 2023 100%
Campus Move-in Oct 2023 0 Oct 2023 100%
ARC Davies Hall Modernization
PM: Duchaine Architect: Contractor:
Scope: Demo and replace Davies Hall
Weekly Update:
Tenative Schedule Start Months Finish % Complete
Prelim Plans Aug 2025 0 Aug 2025
Approvals Aug 2025 0 Aug 2025
Working Drawings Aug 2025 0 Aug 2025
Approvals Aug 2025 0 Aug 2025
Bid and Award Aug 2025 0 Aug 2025
Construction Aug 2025 0 Aug 2025
Campus Move-in Aug 2025 0 Aug 2025
ARC NEC Phase II & III
PM: Besne Architect: LPA Inc Contractor: JOHN F OTTO, INC
Scope: This Project builds a new 31,077 assignable square feet (asf) (49,800 gross square feet) instructional facility adjacent to the existing American River College Natomas Center building. The new building will provide space for instruction in general education, biology and chemistry and provides ADA access compliance and adequate HVAC, power, technology and lighting systems to support these instructional programs. This includes 5,610 asf of lecture space, 16,441 asf of lab space and 9,026 asf of office/admin and miscellaneous support space.
Weekly Update: Current activities: Exterior envelope is nearly complete. Brick is substantially complete; stucco is 90% complete. Glazing is ongoing and approximately 85-90% complete. Interior: production drywall is substantially complete on level 1 & 2. Paint in key areas has begun. Key concerns are: laboratory finishes at level 2, elevator shaft framing (Kone checklist has not been completed), controls and potential issues regarding building mechanical systems that may not be identified until start-up. upcoming activities for June: T-bar ceiling grid, epoxy flooring, finishes, ceramic tile, building energization.
Tenative Schedule Start Months Finish % Complete
Prelim Plans Nov 2019 9 Aug 2020 100%
Approvals Aug 2020 4 Dec 2020 100%
Working Drawings Dec 2020 6 Jun 2021 100%
Approvals Jun 2021 14 Aug 2022 100%
Bid and Award Aug 2022 9 May 2023 100%
Construction May 2023 29 Oct 2025 81%
Campus Move-in Oct 2025 2 Dec 2025 0%
Installation of Restroom Tile
South Exterior Elevation
ARC NEC TAP II & III Offsite Parking
PM: Uhlmeyer Architect: Kier+Wright (civil) Contractor: WESTERN ENGINEERING CONTRACTORS, INC
Scope: Construction of off site parking to support NEC phase II and III. Location of parking lot will be across Via Ingoglia, a short walk to the Natomas Center, and provide approximately 250 stalls. The parking lot is on a shared property with a soon to be constructed softball field for Inderkum HS.
Weekly Update: This project is 100% complete, Jen Mellor (NUSD) has been allowed to open and close the parking lot per HS Softball needs. .................................................................................................................................................................................................. precision striping PO issued - work to be completed week of 5/1 Zellars Concrete on site to complete City Side Walk Restoration work for City Final week of 5/1
Tenative Schedule Start Months Finish % Complete
Prelim Plans Nov 2019 3 Feb 2020 100%
Approvals Feb 2020 9 Nov 2020 100%
Working Drawings Nov 2020 6 May 2021 100%
Approvals May 2021 6 Nov 2021 100%
Bid and Award Nov 2021 4 Mar 2022 100%
Construction Mar 2022 8 Nov 2022 100%
Campus Move-in Nov 2022 1 Dec 2022 100%
Paving and Landscaping completed looking towards Library
Aerial View of Completed Lot
ARC Portable Village 1 & 2 Refresh
PM: Cox Architect: Contractor:
Scope: Costs related to the closure of Davies Hall and Refresh of existing Portable Villages 1 & 2 to support instruction due to closure.
Weekly Update: Fence--Successfully bid well below budget. NTP issued, but project placed on hold per P. Manzo. Rocket Luxury Toilet Trailers set at PV1 and ready for use. PV1 Restroom Project design moving ahead--package submitted to DSA on 5-22. PV3 has been cancelled and replaced with upgrades to PV1, PV2, Raef, STEM, and Science. Started scope review with campus. Waiting on Margaret L. for remaining scope review.
Tenative Schedule Start Months Finish % Complete
Prelim Plans Nov 2023 19 Jun 2025 30
Approvals Jun 2025 1 Jul 2025
Working Drawings Jul 2025 3 Oct 2025
Approvals Oct 2025 4 Feb 2026
Bid and Award Feb 2026 4 Jun 2026
Construction Jun 2026 6 Dec 2026
Campus Move-in Dec 2026 1 Jan 2027
ARC Tech Ed Modernization
PM: ICS Architect: DLR Group Contractor: JOHN F. OTTO INC DBA OTTO CONSTRUCTION
Scope: This Project builds a new 60,552 assignable square feet (asf) (91,000 gross square feet) instructional facility to replace the existing Tech Ed building on the American River College campus. The new building will be used for instruction in Automotive Technology, Welding, Funeral Services and Electronics and provides ADA access compliance and adequate HVAC, power, technology and lighting systems to support these instructional programs. This includes 5,782 asf of lecture space, 50,081 asf of lab space and 4,689 asf of office/admin support. The Project will incorporate existing Tech Ed spaces and surrounding portable buildings, as well as the phased demolition of the existing Tech Ed facility and adjacent portable buildings.
Weekly Update: The project is approximately 99% complete. Move-in of equipment nearly complete as areas are readied for Fall classes. Phase 2 parking paving is complete and landscape has started. Classes are being held in many areas over the summer.
Tenative Schedule Start Months Finish % Complete
Prelim Plans Dec 2019 8 Aug 2020 100%
Approvals Aug 2020 1 Sep 2020 100%
Working Drawings Sep 2020 8 May 2021 100%
Approvals May 2021 12 May 2022 100%
Bid and Award May 2022 4 Sep 2022 100%
Construction Sep 2022 34 Jul 2025 99%
Campus Move-in Jul 2025 2 Sep 2025 75%
Soldering Lab
ARC Tech Ed Temp Housing
PM: Meyer Architect: WESTON & ASSOC MECHANICAL ENGINEERS Contractor: DIVISION 5-15 INC
Scope: Modifications to temp housing to accommodate Tech Ed construction phase.
Weekly Update: Contractor has completed installation and balancing of vent system and electrical work required to house program temporarily while the ARC Tech Ed project is under construction. Project is complete.
Tenative Schedule Start Months Finish % Complete
Prelim Plans Aug 2021 1 Sep 2021 100
Approvals Sep 2021 1 Oct 2021 100
Working Drawings Oct 2021 1 Nov 2021 100
Approvals Nov 2021 1 Dec 2021 100
Bid and Award Dec 2021 2 Feb 2022 100
Construction Feb 2022 1 Mar 2022 100
Campus Move-in Mar 2022 0 Mar 2022 100
Project location
Classroom venting for student projects
ARC Veterans Resource Center
PM: Cox Architect: AE3 Contractor:
Scope: This is a Campus funded project to renovate the Veterans Resource Center in the Student Services building. Project demo's existing space, renovates interior to make it more functional and inviting for users and updates HVAC, Electrical, plumbing and all finishes. Also creates new patio area for the program.
Weekly Update: Plans approved by DSA. Third (final) in-house plan review complete and comments sent to architect on April 11-- Working to coordinate with campus and FM HVAC team for controls work preceding this remodel--this seems to be resolved. Awaiting DSA approved addenda so project can bid. Final estimate came in at just under $1.4M.
Tenative Schedule Start Months Finish % Complete
Prelim Plans Dec 2022 2 Feb 2023 100
Approvals Feb 2023 1 Mar 2023 100
Working Drawings Mar 2023 9 Dec 2023 100
Approvals Dec 2023 18 Jun 2025 100
Bid and Award Jun 2025 3 Sep 2025
Construction Sep 2025 9 Jun 2026
Campus Move-in Jun 2026 1 Jul 2026
CRC 2025 Central Plant Upgrade
PM: Uhlmeyer Architect: Interface Engineering Contractor:
Scope: Upgrade of central plant heating and chilling equipment to meet current and future capacity needs.
Weekly Update: Project Feasibility Study in progress and is expected in approximately 4 weeks. Once study is complete District will evaluate options and select appropriate project scope with which to proceed.
Tenative Schedule Start Months Finish % Complete
Prelim Plans Mar 2025 4 Jul 2025 5
Approvals Jul 2025 2 Sep 2025
Working Drawings Sep 2025 6 Mar 2026
Approvals Mar 2026 6 Sep 2026
Bid and Award Sep 2026 3 Dec 2026
Construction Dec 2026 14 Feb 2028
Campus Move-in Feb 2028 1 Mar 2028
CRC 2025 Stadium Synthetic Turf Replacement
PM: Uhlmeyer Architect: Verde Designs Contractor:
Scope: Project to replace synthetic turf in football stadium which has reached its end of life.
Weekly Update: WCE to be on site for topo survey - date TBD
Tenative Schedule Start Months Finish % Complete
Prelim Plans Mar 2025 4 Jul 2025 50%
Approvals Jul 2025 1 Aug 2025
Working Drawings Aug 2025 4 Dec 2025
Approvals Dec 2025 2 Feb 2026
Bid and Award Feb 2026 3 May 2026
Construction May 2026 3 Aug 2026
Campus Move-in Aug 2026 1 Sep 2026
CRC Affordable Student Housing
PM: Duchaine Architect: Contractor:
Scope: Affordable student housing project to be build on campus as CRC. Funds provided by State - $44,100,000 total for hard and soft costs.
Weekly Update: Project on hold pending siting of new structure.
Tenative Schedule Start Months Finish % Complete
Prelim Plans Nov 2024 7 Jun 2025
Approvals Jun 2025 0 Jun 2025
Working Drawings Jun 2025 9 Mar 2026
Approvals Mar 2026 9 Dec 2026
Bid and Award Dec 2026 4 Apr 2027
Construction Apr 2027 19 Nov 2028
Campus Move-in Nov 2028 2 Jan 2029
CRC CRC Electrical Switch Gear Replacement (SMSR)
PM: Cox Architect: The Engineering Enterprise Contractor: BOCKMON & WOODY ELECTRIC CO
Scope:
Weekly Update: Gear has been ordered with an updated delivery date of 09/22/2025. Pad, Fence and paving complete. Final vault has been set and approved by SMUD. Reviewed needed landscape repairs and contractor plans to address after switchgear set. Temp fence has been removed.
Tenative Schedule Start Months Finish % Complete
Prelim Plans Feb 2022 3 May 2022 100
Approvals May 2022 0 May 2022 100
Working Drawings May 2022 13 Jun 2023 100
Approvals Jun 2023 2 Aug 2023 100
Bid and Award Aug 2023 5 Jan 2024 100
Construction Jan 2024 20 Sep 2025 52
Campus Move-in Sep 2025 0 Sep 2025
CRC Culinary Arts Remodel
PM: Cox Architect: tBP Contractor: F&H CONSTRUCTION
Scope: Reconfiguration of kitchen to better accommodate both Food Service vendor and Culinary program
Weekly Update: Project is substantially complete with Vendor occupying phase 1 and campus using phase 2.
Tenative Schedule Start Months Finish % Complete
Prelim Plans Aug 2021 5 Jan 2022 100%
Approvals Jan 2022 1 Feb 2022 100%
Working Drawings Feb 2022 6 Aug 2022 100%
Approvals Aug 2022 4 Dec 2022 100%
Bid and Award Dec 2022 5 May 2023 100%
Construction May 2023 19 Dec 2024 99%
Campus Move-in Dec 2024 0 Dec 2024 70%
Phase 1 and 2 kitchen
Phase 3 kitchen
CRC EGC Phase II
PM: Cox Architect: DLR Group Contractor: JOHN F. OTTO INC DBA OTTO CONSTRUCTION
Scope: The Long Range Capital Needs Plan and local bond measure M include funds to construct Phase 2 of the Elk Grove Center. This Project builds a new 15,200 assignable square feet (asf) (24,888 gross square feet) instructional facility adjacent to the existing Elk Grove Center Phase 1 building. The new building will provide space for instruction in general education, biology and chemistry and provides ADA access compliance and adequate HVAC, power, technology and lighting systems to support these instructional programs. This includes 3,000 asf of lecture space, 7,200 asf of lab space and 2,400 asf of office/admin and 2,600 of miscellaneous student and faculty support space.
Weekly Update: The project is complete but commissioning of HVAC systems continues and expect to complete mid-august. Contractor completed off-site repairs and awaiting certification from City/County--working through final County billings. Multi Stack has completed repairs of AWHP but minor issues remain and are being addressed. Reprogramming of SOO initiated 07-21 and has minimized faults.
Tenative Schedule Start Months Finish % Complete
Prelim Plans Sep 2019 8 May 2020 100%
Approvals May 2020 2 Jul 2020 100%
Working Drawings Jul 2020 3 Oct 2020 100%
Approvals Oct 2020 9 Jul 2021 100%
Bid and Award Jul 2021 4 Nov 2021 100%
Construction Nov 2021 26 Jan 2024 100%
Campus Move-in Jan 2024 3 Apr 2024 100%
Lobby
Exterior
CRC South Campus Natural Gas Line
PM: Cox Architect: tBP Contractor:
Scope: New natural gas service to College Center to feed Cafeteria.
Weekly Update: Contractor has installed gas line and manifold. Working with PG&E on as-builts and added fees ao meter can be scheduled.
Tenative Schedule Start Months Finish % Complete
Prelim Plans Apr 2024 2 Jun 2024 100
Approvals Jun 2024 1 Jul 2024 100
Working Drawings Jul 2024 1 Aug 2024 100
Approvals Aug 2024 2 Oct 2024 100
Bid and Award Oct 2024 7 May 2025 100
Construction May 2025 3 Aug 2025 85
Campus Move-in Aug 2025 0 Aug 2025
DOC District Wide Infrastructure Master Planning
PM: Meyer Architect: Contractor:
Scope: District Wide Infrastructure Master Planning
Weekly Update:
Tenative Schedule Start Months Finish % Complete
Prelim Plans Jan 2014 6 Jun 2014 0%
Approvals Jun 2014 4 Oct 2014 0%
Working Drawings Oct 2014 7 May 2015 0%
Approvals May 2015 7 Dec 2015 0%
Bid and Award Dec 2015 3 Mar 2016 0%
Construction Mar 2016 22 Dec 2017 0%
Campus Move-in Dec 2017 4 Apr 2018 0%
DOC DO Bond Admin
PM: Meyer Architect: Contractor:
Scope: Project to capture expenses associated with managing the Bond Program
Weekly Update:
Tenative Schedule Start Months Finish % Complete
Prelim Plans Jul 2022 2 Sep 2022 0%
Approvals Sep 2022 0 Sep 2022 0%
Working Drawings Sep 2022 4 Jan 2023 0%
Approvals Jan 2023 3 Apr 2023 0%
Bid and Award Apr 2023 4 Aug 2023 0%
Construction Aug 2023 6 Feb 2024 0%
Campus Move-in Feb 2024 1 Mar 2024 0%
DOC FM Electric Vehicle Charging Stations
PM: Uhlmeyer Architect: TEE Contractor:
Scope: Installation of EV Charging Stations at FM to comply with state required mandate for zero emission vehicle fleet by 2030.
Weekly Update: Issue with CT / Meter - PER SMUD lower rail "lugs to be flipped 180degrees should fix the issue. Contractor to schedule Contractor to be completed with "green card" by county 6/6 SMUD CT (meter) to follow
Tenative Schedule Start Months Finish % Complete
Prelim Plans Sep 2023 6 Mar 2024 100%
Approvals Mar 2024 1 Apr 2024 100%
Working Drawings Apr 2024 3 Jul 2024 100%
Approvals Jul 2024 4 Nov 2024 100%
Bid and Award Nov 2024 3 Feb 2025 100%
Construction Feb 2025 5 Jul 2025 95%
Campus Move-in Jul 2025 0 Jul 2025
DOC LRPD Move to FM
PM: Uhlmeyer Architect: HED Contractor: MESA ENERGY SYSTEMS INC
Scope: Relocate LRPD from Ethan Way to Facilities Management, to include emergency generator & UPS backup, HVAC/Electrical/Data upgrades as needed and warehouse revisions necessary to make room for TI.
Weekly Update: Exterior Flatwork is 50% - ADA parking stall to be cast in place 7/31/2025 interior footings have been dug out - sanitary sewer has been tied - Issue with subgrade (depth of sand fill) to be corrected before interior concrete can be poured. All penetrations in roof are complete with HVAC cans, Solo tube cans, electrical pathway and fire sprinkler drops to within 8' of roof/ceiling assembly. Submittals 56, RFI's 14 Precon meeting 6/2 Conditional NTP issued for 6/2 - Unconditional NTP released 6/4
Tenative Schedule Start Months Finish % Complete
Prelim Plans Jan 2023 11 Dec 2023 100%
Approvals Dec 2023 2 Feb 2024 100%
Working Drawings Feb 2024 3 May 2024 100%
Approvals May 2024 9 Feb 2025 100%
Bid and Award Feb 2025 4 Jun 2025 100%
Construction Jun 2025 8 Feb 2026 16%
Campus Move-in Feb 2026 1 Mar 2026
FLC 2025 EDC Bldg A Foam & Coat Roofing
PM: Blake Architect: Contractor:
Scope: SMSR project to foam and coat Building A at El Dorado Hills Center
Weekly Update: 2025.08.11- 1) Opened Bids on Thursday 8/7/25 and all of the following Roofers were responsive, Brazos Urethane at $176,900, Universal Coatings Inc. at $179,000, Pacific Polymers $118,418 was the lowest and accepted bidder. NOA went out on Monday 8/11/25, Duration 21 Calendar Days. The Estimated Construction Costs $220,000.
Tenative Schedule Start Months Finish % Complete
Prelim Plans Jul 2025 0 Jul 2025
Approvals Jul 2025 0 Jul 2025
Working Drawings Jul 2025 0 Jul 2025
Approvals Jul 2025 0 Jul 2025
Bid and Award Jul 2025 0 Jul 2025
Construction Jul 2025 0 Jul 2025
Campus Move-in Jul 2025 0 Jul 2025
FLC Central Plant Upgrades
PM: Duchaine Architect: Interface Contractor: RODAN BUILDERS, INC
Scope: Upgrade of Central Plant heating and cooling quality and capacity to accommodate near and long term building needs.
Weekly Update: Project is approximately 85% complete. Heating side boilers and pump installation complete. The cooling towers are installed and are currently being piped/plumbed. The chiller pumps are placed and piping/plumbing is in progress. Chillers and pumps are placed and finalizing connections. Chiller and Cooling tower start up scheduled for 5/23/2025.
Tenative Schedule Start Months Finish % Complete
Prelim Plans Nov 2020 9 Aug 2021 100
Approvals Aug 2021 7 Mar 2022 100
Working Drawings Mar 2022 7 Oct 2022 100
Approvals Oct 2022 9 Jul 2023 100
Bid and Award Jul 2023 8 Mar 2024 100
Construction Mar 2024 16 Jul 2025 85
Campus Move-in Jul 2025 1 Aug 2025 85
Chiller with Connections
Cooling Towers 1-4 Yard
FLC Dan's Test.....Delete
PM: Architect: Contractor:
Scope:
Weekly Update:
Tenative Schedule Start Months Finish % Complete
Prelim Plans Jan 2025 0 Jan 2025
Approvals Jan 2025 0 Jan 2025
Working Drawings Jan 2025 0 Jan 2025
Approvals Jan 2025 0 Jan 2025
Bid and Award Jan 2025 0 Jan 2025
Construction Jan 2025 0 Jan 2025
Campus Move-in Jan 2025 0 Jan 2025
FLC EDC Teaching Vineyard
PM: Mirmiran Architect: MSLA (Michael Shular) Contractor: PRO BUILDERS
Scope: Project will create a small teaching vineyard for viticulture program: to include concrete pad for outdoor teaching, ADA pathway and retaining walls if necessary.
Weekly Update: Punch walk performed on 7/16. Due to unforeseen delayed delivery, light pole installation will be completed on September 19.
Tenative Schedule Start Months Finish % Complete
Prelim Plans Sep 2023 3 Dec 2023 100%
Approvals Dec 2023 1 Jan 2024 100%
Working Drawings Jan 2024 3 Apr 2024 100%
Approvals Apr 2024 7 Nov 2024 100%
Bid and Award Nov 2024 5 Apr 2025 100%
Construction Apr 2025 3 Jul 2025 95%
Campus Move-in Jul 2025 0 Jul 2025 0%
FLC Rancho Center Health Hub Project
PM: Duchaine Architect: Lionakis Contractor:
Scope: Project will remodel a portion of the Rancho Cordova Ctr Phase 1 building for new Health programs - CN, EMT & Radiology Tech.
Weekly Update: Bid date 5/15/2025.
Tenative Schedule Start Months Finish % Complete
Prelim Plans Jul 2024 1 Aug 2024
Approvals Aug 2024 1 Sep 2024
Working Drawings Sep 2024 2 Nov 2024
Approvals Nov 2024 3 Feb 2025
Bid and Award Feb 2025 5 Jul 2025
Construction Jul 2025 3 Oct 2025
Campus Move-in Oct 2025 1 Nov 2025
FLC Rancho Cordova Center Phase 2
PM: Uhlmeyer Architect: Studio W Architecture Contractor:
Scope: The Project builds a new 14,200 assignable square feet (asf) (21,000 gross square feet) instructional facility adjacent to the existing Folsom Lake College Rancho Cordova Center building. The new building will provide space for instruction in general education and biology and provides ADA access compliance and adequate HVAC, power, technology and lighting systems to support these instructional programs. This includes 3,200 asf of lecture space, 9,500 asf of lab space and 600 asf of office/admin and 900 asf of miscellaneous support space.
Weekly Update: Project has been split into two parts - Parking Lot and Building.
Tenative Schedule Start Months Finish % Complete
Prelim Plans Sep 2020 7 Apr 2021 100%
Approvals Apr 2021 4 Aug 2021 100%
Working Drawings Aug 2021 5 Jan 2022 100%
Approvals Jan 2022 8 Sep 2022 100%
Bid and Award Sep 2022 9 Jun 2023 0%
Construction Jun 2023 5 Nov 2023 0
Campus Move-in Nov 2023 2 Jan 2024 0
Courtyard view from high up
Interior First Floor Lobby from Entrance
FLC Rancho Cordova Phase 2 Parking
PM: Uhlmeyer Architect: Studio W Contractor: CREEKSIDE COMMERCIAL BUILDERS INC
Scope: Construction of additional off site parking to support Rancho Cordova Center. Project will expand parking lot across Paseo Drive, a short walk to the Rancho Cordova Center, and provide approximately 66 additional stalls.
Weekly Update: Project is complete. Notice of Completion has been requested. Working on final change order for contractor.
Tenative Schedule Start Months Finish % Complete
Prelim Plans Jul 2022 1 Aug 2022 100
Approvals Aug 2022 3 Nov 2022 100
Working Drawings Nov 2022 3 Feb 2023 100
Approvals Feb 2023 3 May 2023 100
Bid and Award May 2023 2 Jul 2023 100
Construction Jul 2023 18 Jan 2025 100%
Campus Move-in Jan 2025 0 Jan 2025 100
Parking Lot Expansion Paving Complete
New Electrical Gear
FLC Science 2.1
PM: SixthDimension Architect: HMC Contractor: JOHN F OTTO, INC
Scope: This Project builds a new 48,900 assignable square feet (asf) (75,000 gross square feet) science building. The new building will be used for instruction in general education, biology and chemistry and provides ADA access compliance and adequate HVAC, power, technology and lighting systems to support these instructional programs. This includes 8,800 asf of lecture space, 28,900 asf of lab space and 11,200 asf of office/admin support. The project will also construct 138 new parking spaces, including 8 new electrical vehicle charging stations (EVCS) in existing parking in front of the Harris Center.
Weekly Update: Project is approximately 90% complete. Activities in progress include, test and balance, equipment start-up, systems programming, audio visual, flooring, and exterior handrails, casework, interior glass and glazing. Anticipated completion June 6, 2025.
Tenative Schedule Start Months Finish % Complete
Prelim Plans Dec 2019 9 Sep 2020 100
Approvals Sep 2020 2 Nov 2020 100
Working Drawings Nov 2020 7 Jun 2021 100
Approvals Jun 2021 13 Jul 2022 100
Bid and Award Jul 2022 4 Nov 2022 100
Construction Nov 2022 31 Jun 2025 90
Campus Move-in Jun 2025 4 Oct 2025 0%
Main Entry
Stairway to Level 2
SCC 2024 Quad Lighting
PM: Blake Architect: Engineering Enterprise Contractor:
Scope: Replace exterior pole lights around quad and campus with new energy efficient LED pole lights.
Weekly Update: 2025.08.11- 1) Design Phase.
Tenative Schedule Start Months Finish % Complete
Prelim Plans Dec 2024 4 Apr 2025
Approvals Apr 2025 1 May 2025
Working Drawings May 2025 2 Jul 2025
Approvals Jul 2025 1 Aug 2025
Bid and Award Aug 2025 3 Nov 2025
Construction Nov 2025 4 Mar 2026
Campus Move-in Mar 2026 1 Apr 2026
SCC Astroturf Synthetic Softball Field
PM: Uhlmeyer Architect: LPA Contractor: PROGRASS WEST INC
Scope: In an effort to address sustainability goals and improve facilities for Los Rios students this project will replace the exis t ing natural grass softball fields at American River College, Sacramento City College and Folsom Lake College with a new synthetic fields. The planned improvements include Removal of the existing natural grass field, New synthetic turf field with associated subdrainage, ADA path of travel improvements as required for the field and Minor ADA improvements to the existing restroom facilities.
Weekly Update: Field complete - ADA Restroom work at Union Stadium start January 6, 2025 with expected completion January 26, 2025
Tenative Schedule Start Months Finish % Complete
Prelim Plans May 2022 4 Sep 2022 100%
Approvals Sep 2022 1 Oct 2022 100%
Working Drawings Oct 2022 2 Dec 2022 100%
Approvals Dec 2022 3 Mar 2023 100%
Bid and Award Mar 2023 3 Jun 2023 100%
Construction Jun 2023 6 Dec 2023 100%
Campus Move-in Dec 2023 0 Dec 2023 100%
SCC CDC Acoustical Improvements
PM: Mirmiran Architect: HMC Contractor: PRO-EX CONSTRUCTION
Scope:
Weekly Update: Punch walk performed on 07/30/2025. Currently waiting for Door HW as last punch item.
Tenative Schedule Start Months Finish % Complete
Prelim Plans Jul 2024 0 Jul 2024 100%
Approvals Jul 2024 1 Aug 2024 100%
Working Drawings Aug 2024 1 Sep 2024 100%
Approvals Sep 2024 3 Dec 2024 100%
Bid and Award Dec 2024 5 May 2025 100%
Construction May 2025 2 Jul 2025 95%
Campus Move-in Jul 2025 1 Aug 2025 0%
SCC Health and Wellness Center Expansion
PM: Blake Architect: Lionakis Contractor: Z SQUARED CONSTRUCTION
Scope: Feasibility study to determine best option for expanding Health Services for Students. Project is in response to a two year grant for $350,000 to establish a mental health program on each campus.
Weekly Update: 2025.08.11- 1) LIONAKIS will be delivering the approved O&M and Warranties the week of 8/18/25.
Tenative Schedule Start Months Finish % Complete
Prelim Plans Jan 2021 5 Jun 2021 100
Approvals Jun 2021 7 Jan 2022 100
Working Drawings Jan 2022 9 Oct 2022 100
Approvals Oct 2022 12 Oct 2023 100
Bid and Award Oct 2023 6 Apr 2024 100
Construction Apr 2024 7 Nov 2024 2
Campus Move-in Nov 2024 1 Dec 2024
SCC Natural Sciences Modernization
PM: Mirmiran Architect: HGA Contractor: BROWARD BUILDERS, INC
Scope: This Project builds a new science building to replace the existing Natural Sciences building.  The new building will be used for instruction in general education, biology and chemistry and provides ADA access compliance and adequate HVAC, power, technology and lighting systems to support these instructional programs.  The total area includes lecture space, lab space and office/admin support.  Upon completion and tenant occupancy of the new science building, the Project will also demolish the existing and adjacent Natural Sciences building. At completion of demo the project will construct a Gazebo at location of old Natural Sciences Building.
Weekly Update: DSA issued Certificate of Occupancy. Wood Veneer installation in progress. Anticipated completion on August 29th.
Tenative Schedule Start Months Finish % Complete
Prelim Plans Jun 2018 2 Aug 2018 100%
Approvals Aug 2018 1 Sep 2018 100%
Working Drawings Sep 2018 11 Aug 2019 100%
Approvals Aug 2019 7 Mar 2020 100%
Bid and Award Mar 2020 9 Dec 2020 100%
Construction Dec 2020 32 Aug 2023 100%
Campus Move-in Aug 2023 1 Sep 2023 100%
Courtyard West and North Elevation
SCC PAC HVAC Replacement - Music Wing (HEERF)
PM: Blake Architect: Carrier Contractor:
Scope:
Weekly Update: 2025.08.11- 1) Conducted Honeywell Demo and Graphics on Tuesday 7/29/25, corrections were needed, Honeywell is working with Allan to rectify.
Tenative Schedule Start Months Finish % Complete
Prelim Plans May 2022 1 Jun 2022 100
Approvals Jun 2022 0 Jun 2022 100
Working Drawings Jun 2022 5 Nov 2022 100
Approvals Nov 2022 0 Nov 2022 100
Bid and Award Nov 2022 7 Jun 2023 100
Construction Jun 2023 0 Jun 2023 99
Campus Move-in Jun 2023 1 Jul 2023
SCC PAC Main Speaker Replacement
PM: Blake Architect: Moniz Architecture Contractor:
Scope: Replace main speakers in PAC that have failed. Speakers hang from above and project will require engineering and DSA approval.
Weekly Update: 2025.08.11- 1) Conducted project design start up meeting on Friday 1/31/25 at the site at 11:30 a.m. 2) Site informed team that the best window for construction would be June 2026 through July 2026, adjusted Bid Schedule accordingly to meet their request. 3) Design Phase.
Tenative Schedule Start Months Finish % Complete
Prelim Plans Feb 2025 6 Aug 2025
Approvals Aug 2025 3 Nov 2025
Working Drawings Nov 2025 2 Jan 2026
Approvals Jan 2026 2 Mar 2026
Bid and Award Mar 2026 3 Jun 2026
Construction Jun 2026 2 Aug 2026
Campus Move-in Aug 2026 1 Sep 2026
SCC SCC South Loop Chiller Replacement (SMSR)
PM: Uhlmeyer Architect: Studio W Architecture Contractor: BP INTERIORS INC
Scope: The SCC South Chiller Replacement project will Demo / remove existing “end of life” (EOL) chiller and associated chilled water piping & existing (refrigerant) evacuation/alarm system, install a new Chiller in its place as well as replace exiting pumps, VFD's and existing Chilled Water Piping/Valves as required • Replace Honeywell Controls System • Replace existing (refrigerant) evacuation/alarm system
Weekly Update: Outstanding issue - Honeywell to provide corrected As-builts
Tenative Schedule Start Months Finish % Complete
Prelim Plans Nov 2022 2 Jan 2023 100%
Approvals Jan 2023 0 Jan 2023 SD 100%
Working Drawings Jan 2023 4 May 2023 100%
Approvals May 2023 4 Sep 2023 100%
Bid and Award Sep 2023 3 Dec 2023 100%
Construction Dec 2023 4 Apr 2024 99%
Campus Move-in Apr 2024 0 Apr 2024
SCC Security Improvement Project - Phase 1 Hardware/Cylinders/Keys
PM: Meyer Architect: Meyer Contractor: BOBO CONSTRUCTION, INC.
Scope: This project has responsibility to provide and install physical door hardware both electrified and non-electrified campus wide. This project will also install owner provided cylinders
Weekly Update: 2023-1-5: Rec'd Midstate PO on 1/4, will coordinate remaining install with Campus. 2022-12-13: Submitted on PO for Midstates and will be completing final buildings in early 2023. 2022-11-16: Working on getting a new PO for Midstate to complete the remaining work in Jan. 2022-8-25: Have substantially completed installation of bypass cores in most buildings, only Lusk, N. Gym Cafeteria and miscellaneous locations remain.
Tenative Schedule Start Months Finish % Complete
Prelim Plans May 2018 3 Aug 2018 100
Approvals Aug 2018 1 Sep 2018 100
Working Drawings Sep 2018 2 Nov 2018 100
Approvals Nov 2018 1 Dec 2018 100
Bid and Award Dec 2018 3 Mar 2019 100
Construction Mar 2019 34 Jan 2022 100
Campus Move-in Jan 2022 1 Feb 2022 100
Hardware awaiting key cylinder install
Building keybox
SCC Swing Space Portable Removal
PM: Blake Architect: Contractor: SIERRA EXCAVATING LLC
Scope: This project will remove all remaining swing space portable buildings on Campus with the exception of one that will house bathrooms and provide storage space for Campus.
Weekly Update: 2025.08.11- 1) Processed Sierra's Retention Pay Application on 7/23/25. 2) Received P.O.'s for Morrow's Surveying and WCE on 7/23/25. 3) Morrow conducted Survey on Tuesday 7/29/25 and provided PDF CAD file on Wednesday 7/30/25, will review and forward to WCE. 4) Scheduled a Site Design meeting for Wednesday 8/13/25 at 12pm.
Tenative Schedule Start Months Finish % Complete
Prelim Plans Oct 2024 0 Oct 2024 100
Approvals Oct 2024 0 Oct 2024 100
Working Drawings Oct 2024 0 Oct 2024 100
Approvals Oct 2024 3 Jan 2025 100
Bid and Award Jan 2025 2 Mar 2025 50
Construction Mar 2025 2 May 2025
Campus Move-in May 2025 1 Jun 2025